Construction Procurement & Contracts Engine

GC selection, bid leveling, GMP/lump sum negotiation, CO compliance, punch list management, and design team evaluation for Development Managers.

GC selectionbid levelingGMP negotiation
Open GitHub source

No packaged download — skills install from the open-source plugin repo. Read the SKILL.md and bundled files below before you install.

How to install a skill →
01 · Problem

GC selection, bid leveling, GMP/lump sum negotiation, CO compliance, punch list management, and design team evaluation for Development Managers.

Derived from the skill’s “Skill description” section.

02 · Who & When

Trigger on any of the following:

  • "Level these bids" or "compare GC bids"
  • "GMP negotiation" or "lump sum contract"
  • "Change order" or "CO review"
  • "Punch list" or "project closeout"
  • "Design team evaluation" or "architect selection"
  • "Construction loan draw" or "draw request review"
  • "Bid leveling" or "scope leveling"
  • "Retainage" or "buyout savings"
  • "AIA contract" or "contract modification"
  • "Builder's risk" or "construction insurance"
  • Any mention of GC selection, procurement, or construction contract terms

Derived from the skill’s “When to Activate” section.

03 · How It's Done Today

Not documented yet for this skill.

04 · What This Skill Changes
## [Workflow Step Name] -- [Project Name]

### Summary
[2-3 sentence executive summary with key recommendation]

### Analysis
[Detailed analysis per process steps above]

### Comparison Table (bid leveling)
| Category | Bidder A | Bidder B | Bidder C | Notes |
|----------|----------|----------|----------|-------|
| Base Bid | $XX.XM   | $XX.XM   | $XX.XM   |       |
| Leveled Total | $XX.XM | $XX.XM | $XX.XM |       |
| Cost/SF  | $XXX     | $XXX     | $XXX     |       |
| Qualitative Score | XX/100 | XX/100 | XX/100 | |

### Key Findings
- [Finding 1 with dollar/schedule impact]
- [Finding 2]
- [Finding 3]

### Risk Items
| Risk | Probability | Impact | Mitigation |
|------|-------------|--------|------------|

### Recommendation
[Clear recommendation with rationale and next steps]

### Action Items
- [ ] [Action 1] -- [Owner] -- [Deadline]
- [ ] [Action 2] -- [Owner] -- [Deadline]

Derived from the skill’s “Output Format” section.

05 · Risks & Caveats
  1. Bid too low: A bid significantly below others (>10%) often means scope gaps or a distressed GC. Never recommend the lowest bidder without verifying scope completeness.
  2. Unlimited GMP amendments: If the contract allows unlimited GMP amendments without owner consent thresholds, the GMP is meaningless. Cap amendment authority at 1-3% of GMP.
  3. Missing lien waivers: Never recommend draw approval without complete lien waivers. A single missing waiver can cloud title.
  4. Markup stacking: Watch for GC marking up their own contingency or marking up sub markups. Double markups are not standard.
  5. Schedule float ownership: If the contract is silent on float ownership, the GC will claim it. Specify shared float or owner-owned float.
  6. Retainage release without punchlist completion: Standard practice is 150-200% of punch list value retained until completion, not full retainage release at substantial completion.
  7. Change order without entitlement: Reject COs where the contractor has no contractual entitlement, regardless of cost reasonableness.
  8. Design team conflicts: If the architect is also providing construction administration, verify independence in reviewing GC change orders.
  9. Bonding from weak surety: Verify surety company A.M. Best rating (A- or better) and Treasury listing.
  10. Insurance gaps during transition: Ensure no coverage gap between builder's risk and permanent property insurance at CO/TCO.